The second domestically produced large cruise ship, the "Aida Huacheng," has completed its trial voyage.
The second domestically-made large cruise ship, "Aida Huacheng", completed its 12-day trial voyage today and docked at port. During the trial voyage, technicians completed the acceptance of key difficult projects such as the main propeller, ship control, endurance, whole-ship vibration and noise, operation of the drone cabin, and release of rescue boats. The trial covered 45 commissioning procedures and 149 test verifications, fully verifying the ship's maneuverability, automation level, safety and comfort, and emission indicators to a high standard. After the trial voyage, the second domestically-made large cruise ship will gradually advance regional completion and system completion and submit the project report to the ship owner, and is planned to be delivered for operation in November this year. After delivery, it will embark on its maiden voyage season from the Nansha International Cruise Homeport in Guangzhou.