Oracle (ORCL.US) denies that the delivery time of the OpenAI project has been delayed. The construction of data centers is still proceeding as planned.

date
13/12/2025
According to the Wise Finance APP, Oracle (ORCL.US) has clarified a report regarding the construction progress of a data center for its major customer OpenAI, denying that the project delivery time has been delayed. Earlier reports stated that due to a shortage of labor and materials, the related data center will be completed in 2028 instead of the originally planned 2027.