Huaneng Power International (600011.SH): Third-quarter on-grid electricity volume fell 9.90% year-on-year.
Zhito Finance APP News: Huaneng Power International (600011.SH) announced that, according to the company's preliminary statistics, in the third quarter of 2026, the company's operating power plants in China completed on-grid electricity of 113.321 billion kWh on a consolidated statement basis, a year-on-year decrease of 9.90%; in the first three quarters of 2026, the company's operating power plants in China completed on-grid electricity of 312.900 billion kWh on a consolidated statement basis, a year-on-year decrease of 5.60%; in the first three quarters of 2026, the average on-grid settlement electricity price of the company's operating power plants in China was 467.63 yuan/MWh, a year-on-year decrease of 2.32%.