Shanghai Lingang Refueling Project ensures the unit is officially put into operation.

date
31/01/2026
In recent days, the 2nd unit of the project for the guarantee unit of the heavy-duty gas turbine test power station in Lingang successfully completed 168 hours of full-load trial operation, marking the full commissioning of the project. The Lingang Heavy-duty Gas Turbine Test Power Station Project is a major national "two-machine" project. The guarantee unit of the test power station is based on independent research and development and extensive international cooperation in the heavy-duty gas turbine special project. It will use mature F-grade and H-grade commercial units on the market to carry out technology research and demonstration. The guarantee unit project will include 1 500MW F-grade unit and 1 670MW H-grade combined cycle unit.