Nomura cuts NVIDIA Corporation (NVDA.US) Rubin shipment forecast for this year by 19%, with SpaceX underpinning next year's growth.
Nomura believes the root cause lies in a succession of problems with components such as HBM4, heat spreaders, and PCBs. At the same time, it is pinning its 2027 growth bet on SpaceX, which will account for 20%-40% of NVIDIA's rack shipments. Even more concerning: although AI server revenue will surge 143% in 2027, it will be driven mainly by soaring prices rather than shipment volumes. Both Nomura and Goldman Sachs warn that shipment growth could plummet to just 3% in 2028.
Nomura cuts NVIDIA Corporation (NVDA.US) Rubin shipment forecast for this year by 19%, with SpaceX underpinning next year's growth.
NVIDIA Corporation's next-generation Rubin chip mass production progress has encountered obstacles. Nomura Securities has significantly cut its 2026 shipment forecast, while pinning 2027 growth on SpaceX's aggressive expansion planbut hidden concerns for 2028 have already surfaced.
In its latest research report, Nomura cut its 2026 Rubin and Rubin Ultra supply forecast by 19% to 1.63 million units, down from its previous expectation of 2.02 million units. A series of component issues has delayed some rack deliveries from late 2026 to early 2027. At the same time, Nomura slightly lowered its 2026 NVL72 rack forecast from 62,000 units to 60,000 units, but immediately raised its 2027 forecast from 66,000 units to 75,000 units, with the incremental demand mainly coming from Elon Musk's SpaceX large-scale capacity expansion plan.
On the market impact side, Nomura expects global AI server revenue to grow 143% year over year in 2027 to US$886 billion, while shipments will grow only 54%. This scissors gap means that the 2027 AI upcycle will be reflected more in prices than in volumesacross-the-board increases in memory, foundry, and supporting component prices are driving a sharp inflation in average selling prices.
This price-driven growth trajectory has raised market concerns about the sustainability of AI capital expenditure. Nomura and Goldman Sachs Group, Inc. (GS.US) both warn that, as technological, regulatory, and financing obstacles emerge, the market may see an "Air Pocket"-style sharp slowdown in 2028, with AI server shipment growth expected to plunge to just 3%.
Rubin mass production blocked: HBM4, heat spreader, and PCB issues emerge one after another
Nomura listed multiple factors causing Rubin's slow ramp in the second to third quarters of 2026: HBM4 had issues in the second quarter and in September respectively; the heat spreader design underwent multiple changes from a two-piece to a one-piece design, and then a plan to switch to a temporary lid; capacitors, PCBs, and other components also encountered obstacles.
Nomura believes the above issues have now largely been resolved and expects Rubin to ramp fully from November, with VR200 rack systems to begin meaningful shipments in early 2027.
The cost of the cut: 2026 Rubin/Rubin Ultra shipments are 19% lower than Nomura's July forecast, with the product mix during the delay shifting back toward Blackwell; 2027 Rubin shipments are also slightly cut by 5% to 8.6 million units because NVIDIA Corporation is allocating more CoWoS capacity to Vera CPU and switch chips.
At the rack level, Nomura expects fourth-quarter NVL72 deliveries to decline quarter over quarter (from 16,000 units to 14,000 units) as customers wait for VR200; deliveries should then rebound to 18,000 units in the first quarter of 2027 and further recover to 20,000 units in the second quarter.
It is worth noting that the Rubin delay has objectively extended Blackwell's life cyclea gap versus the market's previous expectation that Blackwell would become obsolete within two years.
2027's growth engine: SpaceX alone underpins rack demand
Nomura raised its 2027 NVL72 rack forecast to 75,000 units, with the core DRIVE coming from SpaceX's aggressive computing capacity expansion targets. Nomura believes SpaceX has become NVIDIA Corporation's largest customer since the second half of 2026 and expects it to account for 20% to 40% of NVIDIA Corporation's 2027 rack shipments, equivalent to 5 to 10 gigawatts of new computing capacity, with a base-case assumption of about 7 gigawatts.
SpaceX aims to expand its computing capacity to 13 gigawatts by the end of 2027 (with an upper limit of 20 gigawatts), versus less than 3 gigawatts currentlyColossus 1 operates 0.3 gigawatts, and Colossus 2 is expected to reach 2.55 gigawatts after full deployment in December. Achieving Nomura's base-case scale of about 10 gigawatts would require two brand-new hyperscale campuses:
The Starbase project in Texas: total investment of more than US$24 billion, equipped with a self-built gas-fired power station, and already has obtained Texas's first batch of data center construction permits;
The Cochise County campus in Arizona: planned investment of about US$50 billion, covering 747 acres, with 6 gigawatts of full-load power capacity; Nomura estimates it could deliver 4.2 gigawatts of computing capacity.
However, the Cochise County campus has not yet obtained construction permits. Nomura acknowledges that the campus's land-use permit and grid connection agreement still await regulatory approval; although the local utility has expressed willingness to supply power, a formal agreement has not yet been reached. This means that nearly half of Nomura's 2027 SpaceX expansion forecast relies on a project that still carries major uncertainty.
In addition, the IPO wave among neoclouds is also one reason Nomura raised its rack forecastincluding Anthropic's completion of its IPO on November 19, Nomura has observed that companies show more aggressive purchasing behavior before and after IPOs. Nomura expects that in 2027, neoclouds plus SpaceX will together account for 55% to 60% of NVL72 rack purchases, up from 50% to 55% in 2026 and about 30% in 2025.
Same racks, bigger bills: price is the main character
Nomura raised its 2027 AI server revenue forecast by 32%, but its shipment forecast for the same period by only 5%, with the gap entirely due to price increases. Based on Nomura's own data, average selling price per server will jump from about US$132,000 in 2026 to about US$208,000 in 2027, a single-year increase of about 58%, and will rise another about 21% in 2028.
Behind the price increases is the dual push from memory and foundry costs. Nomura explicitly states that it had not previously expected such a large increase in HBM prices in 2027, nor had it expected Taiwan Semiconductor Manufacturing Co., Ltd. Sponsored ADR (TSM.US) to raise prices multiple times in 2027. According to the latest research from Goldman Sachs Group, Inc.'s Asia memory team, the 2027 HBM addressable market is expected to reach US$60 billion and further expand to US$237 billion by 2028this is the source of cost inflation flowing into Nomura's server average selling price model.
At the same time, Nomura cut its general-purpose server/CPU server shipment forecasts by 8% (2026) and 15% (2027), respectively, but revenue in that segment falls only 2% to 5%, also because prices are rising. Nomura also notes that since the second quarter of 2026, actual server motherboard shipments have barely grown, because memory, CPUs, PCBs, power ICs, and passive components are all in severe shortage.
The CoWoS battle: Alphabet Inc. Class C (GOOGL.US) gains share sharply, AMD (AMD.US) faces capacity bottlenecks
At the upstream capacity level, Nomura maintains its forecast of about 2 million wafers of Taiwan Semiconductor Manufacturing Co., Ltd. Sponsored ADR CoWoS capacity in 2027 (up about 80% year over year), and for the first time provides an estimate of about 2.6 million wafers for 2028 (up about 30%). After deducting a buffer of about 10%, actual available capacity is about 1.81 million wafers (2027) and 2.34 million wafers (2028), respectively.
In terms of capacity allocation, NVIDIA Corporation maintains a dominant 54% to 56% share, but the largest share gain comes from Alphabet Inc. Class C: its TPU wafer allocation surges 119% to about 500,000 wafers, with its share rising from about 20% to about 28%, corresponding to about 8.8 million TPU shipments in 2027, of which about 65% will be undertaken by Broadcom Inc. (Broadcom, AVGO.US). However, Alphabet Inc. Class C's share is expected to fall back to about 24% in 2028 because TPU v9 (co-designed with MediaTek) will switch to Intel Corporation (INTC.US) EMIB-T packaging rather than Taiwan Semiconductor Manufacturing Co., Ltd. Sponsored ADR CoWoS; Nomura warns that this switch may encounter substrate and packaging yield issues in the first half of 2027.
AMD (8% to 9% share) faces the dilemma of excessive demand. OpenAI and Meta (META.US) have each announced multi-year AMD deployment plans of 6 gigawatts, equivalent to about 167,000 CoWoS wafers; Anthropic's 2-gigawatt Helios MI450 project alone corresponds to about 500,000 chips and about 55,600 wafers, already equivalent to 40% of Nomura's total 2027 AMD CoWoS allocation (135,000 wafers).
Nomura believes that if these projects are concentrated within 2 to 3 years, existing capacity allocation will be unable to simultaneously meet the needs of OpenAI, Meta, and Anthropic, and only after capacity increases to 250,000 wafers in 2028 can they be absorbed.
Funding gap: who will pay this bill?
Nomura forecasts that AI server revenue will increase by US$522 billion year over year in 2027, while the market's consensus forecast for capital expenditure by the five major cloud service providers increases by only US$331 billion (up 42%). Nomura believes the gap between the two will be filled by better-than-expected spending by cloud service providers and by neoclouds.
On the cloud service provider side, according to Goldman Sachs Group, Inc.'s US internet team, capital expenditure by leading cloud vendors will grow 84% in 2026 and 52% in 2027, then sharply decelerate to 13% in 2028, for a cumulative total of US$1.397 trillion. On the neocloud side, Nomura's forecast relies on this group contributing a large amount of rack purchases, but this is precisely the most fragile link: SpaceX has just raised US$40 billion by pledging chip assets in cooperation with Apollo (APO.US), its CEO has previously warned that neoclouds face a "funding drought," and Gartner even predicts that more than 80% of neoclouds will go bankrupt.
Nomura's report also mentions that Jensen Huang returned to the CEO role on November 23, which may help neoclouds obtain financing support.
The 2028 air pocket: growth may disappear early
Nomura has made the warning clear in the report title: there are risks in 2028. Nomura forecasts that AI server unit shipment growth that year will be only 3%, and NVIDIA Corporation's rack shipments will rise only slightly from 75,000 units to 77,000 units.
From a gigawatt perspective, Taiwan Semiconductor Manufacturing Co., Ltd. Sponsored ADR CoWoS capacity corresponds to about 69 gigawatts of AI computing supply in 2027 and about 98 gigawatts in 2028, while among the AI data center construction projects Nomura tracks, only 37 gigawatts are confirmed or progressing smoothly in 2028, with another 42.7 gigawatts not yet securedchips are being produced faster than the buildings that will house them.
Downside risks for 2028 listed by Nomura include:
Overseas construction ban: Trump has threatened to impose heavy taxes on companies building data centers overseas, which could affect 4.5 gigawatts of new capacity in 2027 and 9.5 gigawatts in 2028, accounting for 9.8% and 15.8%, respectively; US hyperscalers have already begun positioning in response, and Anthropic and Meta are reportedly in talks to build data centers in Japan;
Political risk: after the Democratic Party won gubernatorial elections in Texas, Ohio, and Georgia, about 7% of global new capacity faces delay risk in 2028, and under Goldman Sachs Group, Inc.'s pessimistic scenario that proportion could reach 45%;
Financing pressure: AI has become the market's largest debt-financed sector, and both the size of the funding pool and financing costs face challenges;
Technical bottlenecks: Nomura notes that in 2028 multiple new AI chip technologies and system architectures will hit physical limits, including GPU-on-GPU SoIC packaging, cooling solutions above 3,000 watts, CPO, EMIB-T, high-precision substrates, and orthogonal backplanes, with early signs potentially appearing in mid-2027.
NVIDIA Corporation's next-generation Feynman architecture will be the first GPU-stacked SoIC product exceeding 3,000 watts of thermal design power, and key technologies involved, such as vertical power delivery and microchannel heat spreaders, have not yet been validated in mass production.
This article is reprinted from "Wallstreetcn," author: Dong Jing, GMTEight editor: Zheng Yuyang.
Related Articles
Ruiyuan Fund speaks out: Bullish on China equity returns over the next five to ten years; now is a favorable time to allocate to undervalued, high-quality Chinese assets.

Bank of America after "tearing up its report" concludes: Do "fundamentals" still matter? Narrative first!

Have the dip-buying forces in US stocks disappeared? Retail investors' November net selling of individual stocks hit the worst record since the pandemic.
Ruiyuan Fund speaks out: Bullish on China equity returns over the next five to ten years; now is a favorable time to allocate to undervalued, high-quality Chinese assets.
Bank of America after "tearing up its report" concludes: Do "fundamentals" still matter? Narrative first!

Have the dip-buying forces in US stocks disappeared? Retail investors' November net selling of individual stocks hit the worst record since the pandemic.